Phase 2 of Union Bridge Quarry Replacement Almost Complete : CEG

2022-05-10 09:06:16 By : Mr. Leon yin

Wed November 16, 2016 - Northeast Edition #23 Brenda Ruggiero

The second phase of a quarry replacement project in Carroll County, Md., which involves the installation of the longest continuous curved conveyor ever to be installed in the state, is nearing completion.

The private project for an undisclosed dollar amount is for Lehigh Cement Company LLC. The company is currently replacing its Union Bridge Quarry with a greenfield quarry expansion in the neighboring town of New Windsor.

The Phase 2 contract was awarded to Fay, an i+iconUSA Company, with Scott Wilson serving as senior project manager.

Work on this phase began in October of 2015, and was originally scheduled for completion on Jan. 31, 2017. However, crews currently forecast completion in late 2016.

Phase 2 includes site development services for the development of an initial pit, crusher pad, building pad, and transfer tower pad. Extra work added once the project started included the installation of a haul road and erection of a Mechanically Stabilized Earth (MSE) retaining wall and foundations associated with the new crusher system.

Earthwork includes 1.6 million cu. yds. (1.2 million cu m) of total excavation; 685,000 cu. yds. (523,720 cu m) of overburden removal; and 936,000 cu. yds. (715,623 cu m) of blasting and rock excavation. A total of 1.1 million cu. yds. (841,010 cu m) was placed in controlled fill embankments for the building pad, perimeter berm, and haul road. The haul road connects the initial pit, crusher dump area and building pad, and will allow the owner to begin production mining operations at the completion of the contract.

The building pad is the site for a 13,000 sq. ft. (1,208 sq m) shop/office for quarry administration and equipment maintenance. The shop/office is being constructed under Fay's other Lehigh contract, along with a 4.7-mi. (7.6 km) overland conveyor.

Concrete work on the project includes construction of eight concrete footings for a crusher installed by others, as well as a truck unloading pad at the top of the retaining wall to allow 100-ton (91 t) mining trucks to dump directly into the crusher.

The MSE retaining wall constructed inside the crusher pit created grade separation and access for mining trucks to dump into the crusher. The wall is 50 ft. (15.24 m) high and 400 ft. (122 m) long, with tapered ends. Reinforcement of the wall was much heavier than a standard highway wall due to the height and extreme 294,000 lbs. (133,356 kg) surcharge imparted by loaded 100-ton mining trucks. Up to 11 40-ft. (12-m) long galvanized steel straps per 24 sq. ft. (2.2 sq m) panel were used to reinforce the retained fill. Reinforced fill passing a 3 in. (7.6 cm) sieve was crushed on site from limestone in the quarry.

Fay is concurrently working on Phase 1 of this project, which includes excavation, installation of 9,600 ft. (2,926 m) of box culverts, 11,000 ft. (3,353 m) of slab-on grade, and several foundations for the ultimate installation of a 4.7-mi. conveyor system to enable the client to transport crushed limestone from the quarry to its Union Bridge cement plant. This will be the largest curved conveyor in the state of Maryland.

“The karst geology of this limestone deposit presented significant challenges to the excavation and blasting crews,” Wilson said. “The depth of bedrock was extremely variable due to dissolved limestone and faults. Limestone pinnacles up to 20 feet high were overlain and surrounded by soft, wet clays. A high water table compounded the difficulties, since the crusher pit was excavated 30 feet below an active stream. The fill material in the early portion of the project was excavated from above and in between the limestone pinnacles and consisted of clays and poor quality soil, which made it challenging to build haul roads.”

According to Wilson, the limestone mined in the New Windsor Quarry is more than 900 million years old and will supply the Lehigh Cement plant with more than 70 years' worth of raw materials. The Lehigh Union Bridge plant is the second largest cement producing facility in North America and supplies cement from New York to Indiana. At completion, the New Windsor quarry pit will be more than 400 acres and 700 ft. (213 m) deep.

“The initial stripping and working through the karst layer has been a major challenge that Fay has safely accomplished while maintaining their development schedule. Fay has placed safety as their top priority, meeting Lehigh's high expectation and requirements as well as appropriately addressing community concerns. Fay has been a professional and competent company that will be asked to bid on future projects,” commented Kevin Cove, director of project engineering, Lehigh Cement.

The safety regulations on the project are per the Mine Safety and Health Administration (MSHA), not OSHA. Notable differences in MSHA regulations are: vehicle parking brakes, equipment inspection reports, wheel chocks, and task-specific training. The project included 90 acres of clearing and grubbing and the excavation of 1.6 million cu. yds. of overburden, bedrock, karst, limestone and phyllite material.

In addition, crews excavated a 100 by 100 by 15 ft. (30 by 30 by 4.5 m) sump and constructed a 117,000 cu. yd. (89,453 cu m) berm, a 425,000 cu. yd. (324,936 cu m) building pad and a 345,000 cu. yd. (263,771 cu m) haul road. They also installed a 15,500 sq. ft. (1,440 sq m) mechanically stabilized earth retaining wall and 7,000 linear ft. (2,133.6 m) of 12 in. (30.5 cm) HDPE dewatering line, along with continuous dewatering with 6 to 12 in. (15 to 30.5 cm) pumps.

Major subcontracted jobs include blasting by M&J Explosives of Carlisle, Pa.; clearing and grubbing by Deamer Land Clearing of Mifflintown, Pa.; survey and layout by Johnson Bernat Associates (JBA) of Gaithersburg, Md.; erosion control by Hawkins Erosion Control LLC of Mount Airy, Md.; and photogrammetry (aerial mapping) by Identified Technologies, Pittsburgh, Pa.

Major equipment used on the job includes Caterpillar 740B and Komatsu HM400 40-ton (36 t) articulated trucks; Caterpillar 385 and 349 and Komatsu 490 and 650 production excavators; Komatsu PC200, PC300, and PC360 utility excavators; 65-ton (59 t) Link-Belt rough terrain cranes; Ingersoll Rand rollers; a Caterpillar 825H compactor; and Caterpillar D8T, D10N, D9T, and D6N dozers. Today's top stories Branch Civil Leads I-81 Project in Virginia ABC: Members Invested $1.6B in Construction Workforce Education to Upskill 1.3M in 2021 Newer Asphalt Road Construction Technologies Gain Traction Next Generation Cat 906, 907, 908 Compact Wheel Loaders Joy Compak Next Gen Hydraulic Control System Helps Improve Performance of High Production Longwall Systems Maine Quarry Supplying New Granite for Statue of Liberty Base Upgrade To Protect Eagles' Nests, Part of PA Thruway to Be Built with Blasting Restrictions CTE Recognized as a U.S. Best Managed Company

Branch Civil Leads I-81 Project in Virginia

ABC: Members Invested $1.6B in Construction Workforce Education to Upskill 1.3M in 2021

Newer Asphalt Road Construction Technologies Gain Traction

Next Generation Cat 906, 907, 908 Compact Wheel Loaders

Joy Compak Next Gen Hydraulic Control System Helps Improve Performance of High Production Longwall Systems

Maine Quarry Supplying New Granite for Statue of Liberty Base Upgrade

To Protect Eagles' Nests, Part of PA Thruway to Be Built with Blasting Restrictions

CTE Recognized as a U.S. Best Managed Company

Construction Equipment Guide 470 Maryland Drive Fort Washington, PA 19034 800-523-2200

Construction Equipment Guide covers the nation with its four regional newspapers, offering construction and industry news and information along with new and used construction equipment for sale from dealers in your area. Now we extend those services and information to the internet. Making it as easy as possible to find the news and equipment that you need and want.

Contents Copyrighted 2022, by Construction Equipment Guide, which is a Registered Trademark, registered in the U.S. Patent Office. Registration number 0957323. All rights reserved, nothing may be reprinted or reproduced (including framing) in whole or part without written permission from the publisher. All editorial material, photographs, drawings, letters, and other material will be treated as unconditionally assigned for publication and copyright purposes and are subject to Construction Equipment Guide’s unrestricted right to edit and comment editorially. Contributor articles do not necessarily reflect the policy or opinions of this publication. Read our privacy policy here.